Sebring Rd Area Resurfacing -PAVING DATES ARE APPROXIMATE
-
Sebring Rd - Milling 10/6 - Pave 10/9
-
Annapolis St - THIS STREET HAS BEEN PULLED FROM THE PROJECT. WILL BE ON FOR NEXT YEAR.
-
Lexington Rd - Milling 10/2 -Pave 10/7
-
Phillips Rd - PAVED
-
Francis St - PAVED
-
Link Rd - Milling 10/6 - Pave 10/9
-
School Ave - Milling 10/3 -Pave 10/8
-
Lewis St - PAVED
-
Clinton St - Milling 10/3 - Pave 10/8
-
Blake - Mill 10/2 - Pave 10/7
Van Doren Ave Area Resurfacing -Martino Dr milling to begin September 29th. - ROAD WILL BE CLOSED TO THROUGH TRAFFIC -
Douglas Ave Area Resurfacing - Contractor to begin work October.
- Douglas Ave
- So Lawrence Ave
- Prospect St
- Sydney Pl
- Rose St
Old Georgetown Rd Area Resurfacing -COMPLETE
Howard Ave Area Resurfacing -COMPLETE
Sterling Rd Area Resurfacing - Ready to bid in 2026
-
Sterling Rd
-
Olsen Dr
-
Stewart Ave
-
Stockton Ave
-
Clover Pl