Traffic Safety Bureau

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Traffic Page photo (1)

 Sgt. James Raics 

Traffic Safety Bureau 732-873-5533 Ext. 1089

The officers of the Traffic Safety Bureau handle day to day complaints and issues such as parking, speeding and other moving violations, view obstructions, work zones and roadway hazards. These officers are trained in various fields such as crash investigation and reconstruction, traffic engineering and specialized enforcement. The Traffic Safety Bureau also supervises township school crossing guards and tow services. 

Currently, there are 4 officers assigned to the Traffic Safety Bureau, which includes, Officer Ryan Ellington, Officer Andre Tirado, Officer Robert Meyer and Officer Jelani Lanier.

Street Resurfacing Project Status

Post Date:07/30/2026 11:18 AM

    Sterling Rd Area Resurfacing -Concrete work completed. Milling and paving operations have begun. Delays due to the extreme heat are possible. 

    • Sterling Rd -Paved
    • Olsen Dr - Paved
    • Stewart Ave -Paved
    • Stockton Ave - Paved
    • Clover Pl -Paved
    • Marion Ave -Paved
    • Evelyn - Paved
    • Annapolis St - Milling 7/31 - Paving 83 - 8/4 weather depending

    Cedarbrook Rd Resurfacing -COMPLETED

    Coppermine Rd Area Resurfacing - Milling to begin August 5 

    • Coppermine Rd
    • Alma Ct - Mill 8/5 - 8/6 Paving 8/7
    • Wiley Dr
    • Warren St - Mill 8/5 - 8/6 Paving 8/7
    • Mc Guffy Rd
    • 14th St
    • Samuel PL
    • Howard Ave SBB section

    Highwood Rd Area Resurfacing -Bid Awarded

    • Highwood Rd
    • Old Lane Highwood
    • Neuville Rd
    • Radio Ct
    • Boulder Ln
    • Section of Hawthorne Dr

    Willow Ave Area Resurfacing -Bid Awarded

    • DeMott Lane - Easton Ave to New Brunswick Rd 
    • 9th St
    • Willow Ave
    • 2nd St
    • Alton Dr
    • Treptow Rd

    Randolph Rd Area Resurfacing -Out to bid

    • Randolph Rd
    • Bell St
    • Bort St
    • Sanders Ave
    • Jimmy Ct
    • Campus Dr
    • Belmont Dr

    Canal Rd Resurfacing - In design

    Pierce St (Cedar Grove to Davidson) -Concrete to begin on or about 7/31 - Milling and paving to begin on or about 8/13 - Weather permitting

    New Brunswick Rd (Willow to Cedar Grove) -Out to bid

    Girard Ave Area Resurfacing - In Design

    • Susan Dr
    • Blair Ave
    • Roosevelt Ave
    • Millstone Rd
    • Flower Rd
    • Girard Ave
    • West Point Ave
    • Green St
    • Austin Ave
    • Home St - Small Section
    • Jefferson St
    • Sumner Ave
    • Field St

     Golf View Area Resurfacing -Out to bid

    • Vilet Rd
    • Golf View Dr
    • Carraige Trail
    • Champlain Way

    Fuller St Area Resurfacing - 

    • Burns St
    • Springfield Ave
    • Frank St
    • Fuller St
    • Hillview Ave
    • Livingston Ave
    • Nicole Dr
    • Rieder Ct
    • Barclay Ct
    • Dumont St
    • Marigold Lane

     

     

    Return to full list >>