As soon as we receive the certified rates we will proceed with our billing process. The 3rd quarter is still technically due August 1, 2018 but the grace period will be extended to 25 days from the date the bills are mailed by the tax office. Please note that the mailing date is key date, not the date that you night receive your bill.

At this time, these tax bills will also become available on our secure online payment system at this link.

NESE Proposal

Print
Press Enter to show all options, press Tab go to next option

Overview of Proposal:

(FERC Docket No. CP17-101)

Goal of Williams/Transco for the Northeast Supply Enhancement Project (NESE)

  • Deliver 400,000 dekatherms/day of natural gas to NYC

  • Williams/Transco already has a commitment from National Gas to buy this gas

In Pennsylvania, they plan to add:

  • a 10.2-mile, 42-inch pipeline loop of Mainline D in Lancaster County, PA; and

  • a 21,902 horsepower electric-powered compressor unit at STA200, Chester County, PA (where there’s already 13 compressor units)

In New Jersey & New York, they plan to add:

 

Raritan Bay Loop Pipeline

Sayreville, NJ into & under Raritan Bay

Madison Loop Pipeline

Old Bridge & Sayreville, NJ

 

 

23.5-mile, 26-inch loop (0.16 mile onshore and 23.33 miles offshore) of Transco’s Lower New York Bay Lateral from Mile Post 12.00, southwest of the Morgan Meter & Regulator (M&R) Station in Sayreville, NJ to the Rockaway Transfer Point in New York State waters +a 2,375’ CP Power Cable

 

3.4-mile, 26-inch loop of Transco’s Lower New York Bay Lateral from Compressor Station 207 at Mile Post 8.57 in Old Bridge to Mile Post 12.00, southwest of the Morgan M&R Station in Sayreville                                                                                                                          

 Compressor Station 206 Franklin Township (Somerset County)

 

New compressor station consisting of two natural gas-powered turbine-driven compressor units planned to be built on a 52-acre lot -total horsepower: 32,000

Two 50-foot smokestacks where:

  • Exhaust Exits At 210,000 cubic feet per minute
  •  Exit Temperature Is 849.2 degrees fahrenheit

Emissions include:

  • 13 pounds of carbon monoxide per hour
  • Ammania, formadehyde, benzene, and other toxic airborne carcinogenic chemicals

 

Acres Affected by the Northeast Supply Enhancement Project

 

Onshore

 

During Construction

(includes workspace, access roads & contractor yards)

 

During Operation

 

NJ

 

95.3

 

29.9

 

PA

 

236.8

 

29.8

 

Total

 

332.0

 

59.7

 

 

Offshore

 

During Construction

(includes excavation – pipe installing & dredging for backfill, vessel mooring & temporary piles)

During Operation

(includes easements)

 
 NJ water  

4,427.8

 

22.4

 NY waters  

10,922.2

 

422.6

 Fed waters  

235.7

 

-

 Total  

15,585.7

 

445.0

 

Williams/Transco claims that 117.2 acres of seafloor will be directly impacted by construction activities:

82.6 acres for the pipeline installation & vessel anchoring/mooring + 36.6 acres to dredge for backfill

Pipeline Construction in Raritan Bay – Navigation Channels

 

Horizontal directional drilling

(HDD)

 

Open Cut

(Clamshell Dredge, Jet Trencher

& Hand Jet

Ambrose Channel

(Reach B) 

NJ
waters

 Raritan Bay
(East Reach)

 NY
waters

Madison Shore Approach

NJ
waters

Chapel Hill (North Channel)

NY
waters

Construction of offshore pipeline

  • 9 months (quarter 2 of 2019 to end of 2019) is the current proposal

  • 7 days per week, 24 hours per day (weather permitting)

*Short portions will be completed separately; need to follow restricted times for to fish or shellfish harvest areas and/or spawning & larval periods.

Note: This is the adjusted (current) proposed route due to anchorage issues. Now = 17.38 miles in NY waters.

Timeline of the NESE Proposal